Installation Week #2

12 trucks with total of 49 tiles and lids have been delivered so far,
39 tiles is installed and 10 in storage for next week,
Thursday we had rain and high wind speeds and managed only to place one tile,
we compensated for it on Friday by placing 15 tiles!
Calculated tile rate is 8 per day, so we are still on track!
 
The container installation team from ASTRON successfully installed all equipment and cables.
 
The LBA surface have been accepted and the contractor has completed the ground work and left us.
 
On Monday four summer-workers will be added to our installation staff, they will help us out until the end of LBA installation.
 
The fence installator will arrive on Monday, why we have to move our equipment and work-shed inside the fence area.

39 tiles on place (June 10 2011)