Installation Week #1

Delivery of tiles and lids have continued, six trucks have been sucessfully unloaded so far
20 tiles with lids is now stored and secured under tarpaulins at the site.
Cords with over thousand bowline knots tied to anchors
860 meters fleece is nailed down along the antenna alleys
520 ground anchors pounded and secured 60 cm down in the ground
Temporary plywood road is buildt
The crane placed at first installation position
Platform for unfolding mounted
First HBA antenna placed

The surface on LBA field is leveled and finished,
acceptance measurements will be carried out on Wednesday the 8th.
Everything is going according to plan!!

Part of the installation team, finished with tile one (June 01 2011)